Builder sued over late delivery? The STJ has set limits on the damages

The law and the repetitive appeal rulings of the STJ (Brazil's Superior Court of Justice) define what the buyer can claim when construction runs late. The defense starts by checking the agreed grace period, the contractual penalty, the period of delay and the date on which possession was made available.

Defense across BrazilProfessional confidentialityReplies on WhatsApp

What the law says

The 180-day grace period and the buyer's two options

Art. 43-A of Law 4,591/1964, added by Law 13,786/2018, allows delivery up to 180 calendar days after the agreed date, without termination of the contract and without a penalty, provided that the grace period is stated expressly, clearly and prominently in the contract.

Once that period has passed without fault on the part of the buyer, the buyer may seek termination, with a refund of everything paid plus the contractual penalty, within 60 days (§ 1º), or keep the contract and receive damages of 1% per month on the amount actually paid to the developer, pro rata die (§ 2º). The two penalties cannot be combined (§ 3º).

What the STJ says

Penalty, lost profits and construction-period interest

Tema 970. The penalty clause for delay (cláusula penal moratória) serves to compensate for the delay and, when set at an amount equivalent to rent, rules out combining it with lost profits (REsp 1.498.484/DF).

Tema 971. If the standard-form contract provides a penalty only for the buyer, that penalty serves as the benchmark for the damages owed by the seller, converted into a sum of money through judicial assessment (arbitramento) (REsp 1.614.721/DF).

Tema 996. The delivery date cannot be tied to the approval of financing. The buyer's loss is presumed and corresponds to the rent of a similar property, until direct possession is made available. Charging construction-period interest (juros de obra) after the agreed deadline, including the grace period, is unlawful (REsp 1.729.593/SP).

The STJ's 3rd Panel (3ª Turma) allows lost profits when the contractual penalty is lower than the rent (REsp 2.025.166). For this reason, the wording of the penalty clause carries weight in the defense.

Moral damages

Delay does not automatically give rise to moral damages

According to the STJ, a mere breach of contract does not, by itself, give rise to moral damages (dano moral). The exception is a delay over a long period, which may justify compensation depending on the circumstances (AgInt no AREsp 3.107.617/RJ, 4th Panel, published in the DJEN, the national electronic court gazette, on June 19, 2026).

Requirements

What the defense examines

Summary table

Delivery date, grace period and penalties shown prominently.

Dates

Contractual deadline, habite-se (occupancy permit) and availability of the keys.

Contractual penalty

Amount of the penalty clause compared with the rent.

Causes of the delay

External events documented during construction.

Buyer conduct

Outstanding payments or documents.

Charges

Construction-period interest, adjustment index and other charges.

Source: Law 4,591/1964, art. 43-A (Law 13,786/2018); STJ, Temas 970, 971 and 996; REsp 2.025.166; AgInt no AREsp 3.107.617/RJ.

What is your case?

Situations the firm handles

Complaint

Claim for rent and penalty at the same time

Challenge to the combination under Tema 970.

STJ, Tema 970
Grace period

Delay within the 180 days

Review of the agreed grace period clause.

Law 4,591, art. 43-A
Moral damages

Claim for moral damages due to the delay

No presumed damage from a mere breach.

STJ, AgInt no AREsp 3.107.617
Termination

Buyer wants to undo the contract

Refund and penalty within the limits of § 1º.

Law 4,591, art. 43-A, § 1º
End date

Keys available but not collected

Damages end when possession is made available.

STJ, Tema 996
Volume

Portfolio with many similar lawsuits

Standardized arguments and settlements based on set criteria.

Litigation management
This page provides general information, does not replace an analysis of the case and there is no guarantee of results.

Step by step

How the firm works

  1. Assessment. We read the contract, summary table, complaint and construction documents.
  2. Calculation. We check periods, amounts paid and what the law and the STJ allow the buyer to claim.
  3. Defense. Statement of defense, hearings and appeals, with the arguments that apply to the case.
  4. Portfolio. For developers with many lawsuits, we standardize arguments, reports and settlement criteria.
+5 thousand cases handledTen years of law practicePractice before the STJ and the STFFeatured in G1, UOL, Estadão and TV Globo

Case review

Let us review your company defense

Answer the questions, one at a time. At the end you can attach documents, which go straight to a folder in the firm's Drive, and send the summary via WhatsApp. Everything is protected by attorney-client confidentiality.

Common questions

Frequently asked questions

Is the 180-day grace period clause valid?

The law allows a grace period of up to 180 calendar days when it is agreed expressly, clearly and prominently in the contract.

Can the buyer receive the penalty and rent at the same time?

Under Tema 970, a delay penalty equivalent to rent rules out combining it with lost profits. When the penalty is lower than the rent, the 3rd Panel allows lost profits to be claimed.

Until when do damages accrue?

Under Tema 996, the presumed rent is owed until direct possession is made available to the buyer.

Does a delay always give rise to moral damages?

The STJ holds that a mere breach does not give rise to moral damages by itself, except for delays over a long period.

Do you serve companies from other states?

Yes. We work throughout Brazil, with electronic court filings and online meetings.

How does engagement work?

After the analysis, the firm sends a written fee proposal. For portfolios with many lawsuits, there is a monthly retainer.

Lawyer for builder defense in construction delay cases

SPD Advocacia represents builders and developers from all over Brazil in lawsuits over late delivery of properties, with a defense based on Law 13,786/2018 and the STJ repetitive appeal rulings.

Grace period and penalty

The law allows a grace period of up to 180 days and sets out the consequences of delay beyond that period.

STJ repetitive appeal rulings

Temas 970, 971 and 996 deal with combining penalties and lost profits, reversing the penalty clause and construction-period interest.

Informational content, in accordance with OAB (Brazilian Bar) Provision 205/2021. Each case depends on a review of the documents, and no result is promised.